S.R. 0019 Section A20
Michael Kilgore
After
Before
Cost: $782,385
Client: PennDOT District 12-0
Contact: Jeremy Shaneyfelt, P.E. (724-439-7321)
Project Letting: October 2021
S.R. 0019, Section A20 (ECMS #76027) - - Greene County - The project consisted of the replacement of the existing slab bridge carrying SR 0019 over Shannon Run with a precast reinforced concrete box culvert. Approach roadway construction was minimal. Wades Run, which parallels S.R. 0019 to the west, was relocated away from roadway in order to accommodate the roadway typical and fill slopes and to minimize future slope maintenance. To mitigate for the stream impacts, items including in-stream log structures and tree plantings were included with the project. Traffic was maintained via detour during construction.
S.R. 0011, Sections 114/115 & SR 0487, Section 100
Michael Kilgore
Cost: $6.8 million
Client: PennDOT District 3-0
Contact: Justin Gochenauer, P.E. (717-221-2010)
Project Letting: September 17, 2020
Bloomsburg Reconstruction Project - Columbia County - This project consists of 1.371 miles of urban arterial roadway resurfacing/reconstruction, drainage and guide rail updates, pedestrian facility improvements, retaining walls, intersection safety improvements including new traffic signals, roadway lighting and parking meters, and other miscellaneous items.