![]() ![]() Cost: $714,000 Project Length: 1,446 LF Client: PennDOT Engineering District 2-0 Contact: Mr. Erik Brown, P.E. (814-768-0722) Water Street Relocation Project – This project included the relocation of 1,028 LF of roadway and an intersection improvement with S.R. 3006. The project involved coordination with an adjacent railroad and FEMA. A FEMA Conditional Letter of Map Revision (CLOMR) is currently being prepared for the project. BACK |
||||||||||