![]() ![]() Image 1 Image 2 Image 3 Cost: $1.388 million Client: PennDOT Engineering District 9-0 Contact: Bill Ratchford The Poplar Run Bridge was a job designed using the PennDOT BRADD program. The structure length is 80'-0" c-c of brgs, it has a roadway width of 30'-3", it has a skew of 45 degrees and galvanized reinforcing was used in the deck and barriers. It was constructed in 3 months, June to August, to coincide with the summer break from school and eliminate any conflicts with school bus routing. BACK |
||||||||||