Cost: $1.22 Million
Project Length: 737.6 Feet
Client: Engineering District 9-0
Contact: Ms. Monica Farabaugh (814-696-7160)

Clearfield Creek Bridge Replacement - This project included a single span (96.6’ c/c brgs.) precast concrete
spread box beam bridge over Clearfield Creek. The project also included 641’ of approach roadway reconstruction.